Resurfacing to take place in Eastington

Published
30.03.2017

Work will shortly be taking place on the A419 during daytime closures.

news

 

The road has reached the end of its life and now needs to be resurfaced. It will be closed between 10th to 26th April, from 7am to 5.30pm.

Almost the entire length of Spring Hill from the junction with Bath Road to just short of the roundabout at A419 will be resurfaced. Work will start at the north end (near the A419 roundabout) and progress southwards toward Eastington Village.

The road will be reopened for the bank holidays and the weekends, except for Sunday 23 April when the Eastington roundabout outside the village shop will be resurfaced.

Access for residents and businesses will be maintained as long as it is safe. 

People may need to allow extra time for their journeys, although only three days of the scheme will coincide with school term time (23 to 26 April).

Diversions will be clearly signposted.