Home

We use cookies to ensure that we give you the best experience on our website. The cookies cannot identify you.
If you continue to use this site we will assume that you are happy with this.
If you want to use the sites without cookies or would like to know more, you can find out more on the Information Commissioner's web site.
You can see full details of the cookies we use on gloucestershire.gov.uk/cookies/

Skip to main content
A40 Over Roundabout - overnight road closures

A40 Westbound (between Longford Roundabout and Over Roundabout) will be closed overnight between 7pm – 6am until 22 June.

Please note: The need for these overnight closures depends on the progress of the current sheet piling work. The situation is under constant review and the closures will be lifted as soon as possible.

 

A40 Over Roundabout Improvement Scheme

The A40 Over Roundabout is located to the northwest of Gloucester and is the primary point of entry into the city for vehicles travelling from the west.

Highways England carried out the first phase of the planned improvement works for this roundabout. That scheme was called the A40 Over Roundabout western approach widening and completed in March 2015. This consisted of widening the A40 eastbound approach to three lanes to allow a dedicated right turn lane, and also widening the roundabout carriageway on the northern side. A pedestrian crossing was moved to a better location and the lighting was improved within the vicinity of the works.

About the new scheme

The following junctions along the route have been identified for improvement.

  • A417 north: widening of the southbound approach to the roundabout entry to provide three lanes at the junction stop line.
  • A40 east: widening of the westbound approach to the roundabout entry to provide three lanes at the junction stop line.
  • A40 Roundabout - general: The addition of a third circulatory lane within the roundabout.

Purpose of the scheme

The overarching goal is to provide a free flowing link for traffic along the currently heavily congested A40 roundabout.    

The key objectives have been identified as:

  • Reduce journey times, for all users as well, on the A40 between Highnam Roundabout / Longford Roundabout / Gloucester City Centre.
  • Improve journey time reliability on the A40 between Highnam Roundabout / Longford Roundabout / Gloucester City Centre.
  • Improve the connectivity and capacity of the strategic road network between the Forest of Dean and Gloucester / Cheltenham / Tewkesbury / the M5.

The current programme for the A40 Over Roundabout scheme is as follows:

  • Business case submission - October 2016
  • Business case approved by LEP - December 2016
  • Meet the contractor event - 23 April 2018
  • Construction start - 30 April 2018
  • Construction end - August 2018

Construction work is now underway

Work started on 30 April and will last for 18 weeks, finishing in August 2018. 

There will be no lane closures between 7am – 9:30am and 3:30pm – 6pm throughout the scheme.

All daytime works will be completed using lane closures with the roundabout remaining open. Delays are expected but access will still be possible.

Although some weekend working may be necessary, the majority of the work will take place on weekdays. At present there are only two weekends identified (4 - 5 and 11 - 12 of August) where work will be carried out to resurface the roundabout  - see details below. Further information on road closures will be provided at the time.

Road Closures:

A40 Westbound (between Longford Roundabout and Over Roundabout) will be closed overnight between 7pm – 6am until 22 June.The diversion can be viewed here.

Please note: The need for these overnight closures depends on the progress of the current sheet piling work. The situation is under constant review and the closures will be lifted as soon as possible.

Resurfacing of the roundabout will take place over two weekends in August (4 – 5 and 11 – 12 August). Road closures will be in place from 7pm Friday evening through to 6am Monday morning. Please note that further restrictions will be in place during the resurfacing of the roundabout but access will be maintained where possible.

More details and traffic advice will be issued nearer the time.

Construction Update Bulletins

Please Note: If you would like to be added to the distribution list for these bulletins please contact christian.chambers@britanniaconstruction.co.uk

Bulletin 1 - 17 May 2018

Bulletin 2 - 31 May 2018

Help us improve Gloucestershire County Council

Don’t include personal or financial information like your National Insurance number or credit card details.