Home

gloucestershire.gov.uk uses cookies to make the site simpler.
Find out more about cookies

Skip to main content
A417 Over Causeway - Bridge Maintenance

Essential bridge maintenance work on the Over Causeway in Gloucester starts on 17th September until 12th October overnight between 8pm and 6am on weekdays.

19th September UPDATE - the bridge work that was scheduled to commence this week has now been postponed until Monday 24th September, due to the weather forecast.

One side of the carriageway will be open at all times to minimise disruption.

Work will begin on the A417 northbound, towards the Over Roundabout, meaning the lane will be fully closed over night. Weather depending, this should take around two weeks. Work will then switch to the southbound carriageway, towards the city centre.

A40 Over Roundabout Improvement Scheme

The A40 Over Roundabout is located to the northwest of Gloucester and is the primary point of entry into the city for vehicles travelling from the west.

Highways England carried out the first phase of the planned improvement works for this roundabout. That scheme was called the A40 Over Roundabout western approach widening and completed in March 2015. This consisted of widening the A40 eastbound approach to three lanes to allow a dedicated right turn lane, and also widening the roundabout carriageway on the northern side. A pedestrian crossing was moved to a better location and the lighting was improved within the vicinity of the works.

About the new scheme

The following junctions along the route have been identified for improvement.

  • A417 north: widening of the southbound approach to the roundabout entry to provide three lanes at the junction stop line.
  • A40 east: widening of the westbound approach to the roundabout entry to provide three lanes at the junction stop line.
  • A40 Roundabout - general: The addition of a third circulatory lane within the roundabout.

Purpose of the scheme

The overarching goal is to provide a free flowing link for traffic along the currently heavily congested A40 roundabout.    

The key objectives have been identified as:

  • Reduce journey times, for all users as well, on the A40 between Highnam Roundabout / Longford Roundabout / Gloucester City Centre.
  • Improve journey time reliability on the A40 between Highnam Roundabout / Longford Roundabout / Gloucester City Centre.
  • Improve the connectivity and capacity of the strategic road network between the Forest of Dean and Gloucester / Cheltenham / Tewkesbury / the M5.

The current programme for the A40 Over Roundabout scheme is as follows:

  • Business case submission - October 2016
  • Business case approved by LEP - December 2016
  • Meet the contractor event - 23 April 2018
  • Construction start - 30 April 2018
  • Construction end - September 2018

Construction work is now underway

Work started on 30 April and will last for 18 weeks, finishing in September 2018. 

There will be no lane closures between 7am – 9:30am and 3:30pm – 6pm throughout the scheme.

All daytime works will be completed using lane closures with the roundabout remaining open. Delays are expected but access will still be possible.

Although some weekend working may be necessary, the majority of the work will take place on weekdays. Resurfacing works were carried out at the roundabout over the weekends of  4 - 5th and 11 - 12th August and were finished on Saturday 18th August.

Overnight piling works have now finished

Here is a video update on the scheme from Cllr Vernon Smith, cabinet member for highways:

 

Road closures

Road closures at Over Roundabout for resurfacing, 7am to 12 midnight on Saturday 18 August:

  • A40 Westbound from Longford Roundabout to Over Roundabout
  • A417 Northbound from Over Causeway to Over Roundabout
  • A417 Southbound from Over Roundabout to Over Causeway

Plan of closures

Diversion map:
Westbound diversion

Please note only the yellow diversion route will be signed during the closure as it is suitable for all vehicles.

 

Construction update bulletins

Please Note: If you would like to be added to the distribution list for these bulletins please contact christian.chambers@britanniaconstruction.co.uk

Bulletin 1 - 17 May 2018

Bulletin 2 - 31 May 2018

Bulletin 3 - 14 June 2018

Bulletin 4 - 28 June 2018

Bulletin 5 - 13 July 2018

Bulletin 6 - 27 July 2018

Bulletin 7 - 10 August 2018

Help us improve Gloucestershire County Council

Don’t include personal or financial information like your National Insurance number or credit card details.