What are the timescales for the scheme?

In this section

 Key milestones for the Arle Court Transport Hub are:

  • Early 2022: Gloucestershire County Council submitted the Multi Storey Car Park planning application  

  • Early 2022: Opportunity for members of the public to comment on the Multi Storey Car Park planning application 

  • June 2022: Some enabling site work will begin to construct new accesses and widen Grovefield Way along with drainage and landscaping improvements. The P&R will remain open during this time. 

  • July 2022: Multi storey car park planning application approved. 

  • November 2022: Revisions to planning submitted. 

  • March 2023: Enabling site work completed.  

  • May 2023: start of construction  

  • Autumn 2024: Estimated end of construction  