Stoke Orchard

Stoke Orchard Traffic Mitigation Scheme

Construction of the Stoke Orchard Traffic Mitigation Scheme will commence on 26 October 2026 and is expected to take approximately four weeks to complete. The works will require temporary road closures for the first three weeks of the programme, followed by temporary traffic lights during the final week. Every effort will be made to minimise disruption and maintain access where it is safe to do so; however, residents and road users should expect some delays to journey times.

Stoke Orchard Traffic Calming Scheme

Scheme Background

The Stoke Orchard Highways Improvement Scheme aims to reduce traffic impacts associated with the M5 Junction 10 Improvements Scheme. The project will introduce traffic calming measures to improve road safety, reduce vehicle speeds, and help minimise noise within the village.

What is proposed

  • Priority traffic calming features (build-outs) to give priority to vehicles leaving Stoke Orchard village. These will be located near St James’ Church and The Elms.
  • Reduction of the speed limit through the village from 30 mph to 20 mph.
  • A new pedestrian footpath linking the traffic calming features near St James’ Church to the existing bus stop at the junction of Mill Lane and Stoke Road.
  • New street lighting columns, along with upgrades to existing lighting along Stoke Road.

Key Milestones

Completed

  • June 2024 – Examination of the M5 Junction 10 DCO, including Stoke Orchard mitigation requirements
  • September 2024 – Project team attended a community information event 
  • June 2025 – Development Consent Order granted by the Secretary of State
  • June 2025 – Stage 1 and 2 Road Safety Audit completed
  • July 2025 – Detailed design of the scheme completed
  • 20 August to 14 September 2026 – The Traffic Regulation Order to reduce the speed limit from 30 mph to 20 mph was advertised. 

Still to come

  • 26 October- 20 November 2026 - Construction works.

Construction Programme

Construction to commence on 26 October 2026 and is expected to take approximately four weeks to complete, ending on the 20 November 2026. 

To allow the works to be carried out safely and efficiently, a series of temporary road closures will be required along Stoke Road. These closures have been planned to minimise disruption while enabling the scheme to be delivered as quickly as possible.

Please note that all construction activities remain subject to weather conditions, unforeseen technical issues and operational requirements. As such, programme dates may be subject to change.

Phase 1: Week 1 & 2

Stoke Road will be closed between Mill Lane and Armstrong Road. Works during this phase will include:

  • Utility connections for new street lighting.
  • Construction of one of the two priority build-outs.
  • Construction of a new pedestrian footpath.
  • Associated civil engineering works.

Phase 2: Week 3

Stoke Road will be closed between Armstrong Road and The Elms. Works during this phase will include:

  • Construction of the second priority build-out.

Phase 3: Week 4

The final week of the programme will focus on:

  • Installation of enhanced road markings and lining throughout Stoke Road.
  • Completion of any remaining minor works.

Road closures and diversion routes

Resident Access

Properties located within the closure area will continue to be accessible. Access to property frontages will be permitted whenever it is safe to do so; however, residents should expect some delays while works are taking place.

General Access

To ensure the safety of pedestrians, road users and the workforce, vehicular access through the closed section of road will not be permitted during working hours. Clearly signed diversion routes will be in place throughout the closure period.

Diversion Routes

Diversion routes will be clearly signed throughout each phase of the works to help road users navigate around the closures safely.

Community Engagement

We will continue to keep residents informed through the Gloucestershire County Council website and local communications, including updates ahead of construction.

How to get in touch

If you have any questions about the scheme, you can contact us by emailing m5junction10@gloucestershire.gov.uk or by calling 08000 514 514.