County resurfacing works

As part of our promise to invest £150 million in the county’s roads, we are committed to work on the roads in all seasons.

Investment and improvement of Gloucestershire’s highways network is one of our main priorities and we will always endeavour to deliver the maximum number of schemes we can each year, this means working over the winter.

Please check our online schedule below to find out when crews will be working on roads near you. Look out for details on local signs too.

 


How road closures may affect you?

We understand that road closures might cause some disruptions to you and may interrupt your regular journeys, however it is necessary in order for us to repair the road safely.

 

Check this website page, social media and local signs for the latest update.

Many aspects need to be taken into consideration when planning works, however our resurfacing programme is dependent on several factors. It can be affected by things like; heavy rain, changes in temperatures and other weather events, as well as plant breakdown and unforeseen technical issues that arise once work has begun.

As the work involves hot asphalt and large equipment, we will be unable to allow traffic through the Road Closure. If you normally drive into or out of the Road Closure during the hours when the closure is in place, we ask you to please make alternative arrangements.

In exceptional circumstances, some level of access may be considered on a case by case basis but only where it does not impact our ability to undertake the necessary works and where it is safe to do so.

Please see the FAQ Leaflet for further details.

If you usually park on the road within the road closure, you will need to find alternative parking nearby during the hours of the road closure. There is a possibility that your vehicle may be towed out of the area if it is obstructing the works. 

Off-Road parking will not be affected however vehicle access will only be granted in exceptional circumstances where is does not impact our ability to undertake the works and where it is safe to do so.

We always consider night working as an option but it is often not feasible due to environmental restrictions related to noise, particularly in residential areas.

We appreciate that any road closure could have an impact on business operations, however to deliver the works as quickly and efficiently as possible, we kindly ask you to work with us. Where appropriate, we will display a ’Businesses open as usual’ sign. To help us to complete the works with the least disruption to you, we ask you to:

  • Reschedule your deliveries to outside of our working hours
  • Where possible, please consider if staff can park elsewhere during our operational hours or share a lift to work to limit the number of vehicles needing access. Access to vehicles will only be considered on a case by case basis but only where it does not impact our ability to undertake the necessary works and where it is safe to do so.
  • Let your customers know that you will be open, and that they can still access you on foot

We will always send out letters a few weeks before we start work to share as much information as possible with people near by. If we know lots of people could be affected we will send information to local media outlets to help publicise what we are doing. We have a news section on our website and a regular newsletter which you can subscribe to here.

Please check your letter for more information, check the FAQ Leaflet provided with your letter or using the link on this page.

Alternatively call our helpline on 08000 514514 if you cannot find what you’re looking for.

 

Resurfacing Programme - July/August 2019

 

Resurfacing works are delivered Monday to Friday, scheme dates below do not include weekends unless otherwise stated.  (Updated on 19th July 2019)

 

UPDATE:  Due to weather conditions the A46 Cheltenham Road, Painswick will not be completed tonight as scheduled and the road will remain open. Works will be completed during an evening next week under local traffic management, a full road closure will not be required. We apologise for any inconvenience caused.

 

UPDATE:   Due to unforeseen operational issues the resurfacing works planned to take place on Station Road, Woolaston, will now be postponed until later this year, further updates will be provided in due course. We apologise for any inconvenience caused.

 

 

Scheme

Operational hours

Planned Start Date

Planned End Date

B4063 Cheltenham Road, Longlevens

19:00 to 07:00

08/07/2019

22/07/2019

A46 Cheltenham Road, Painswick

19:00 to 07:00

16/07/2019

TBC

A40 Cheltenham Road, Dowdeswell

19:00 to 07:00

16/07/2019

29/07/2019

3/83 Stoke Road, Stoke Orchard

19:00 to 07:00

18/07/2019

24/07/2019

3/7 Woolaston Common, Woolaston

07:00 to 19:00

24/07/2019

25/07/2019

A4136 Gloucester Road & A4136 New Road, Mitcheldean

09:30 to 15:30

25/07/2019

08/08/2019

B4633 Gloucester Road, Cheltenham

19:00 to 07:00

25/07/2019

13/08/2019

3/365 Brockworth Road, Churchdown

07:00 to 19:00

26/07/2019

26/07/2019

3/4 Station Road, Woolaston

08:30 to 19:00

TBC

TBC

 

Detail of resurfacing works in your area

 

3/7 Woolaston Common, Woolaston

Resident Letter     Diversion Route

 

A4136 Gloucester Road & A4136 New Road, Mitcheldean

Resident Letter     Diversion Route

 

A40 Cheltenham Road, Dowdeswell

Resident Letter     Diversion Route

 

 

B4633 Gloucester Road, Cheltenham

Resident Letter     Diversion Route

 

B4063 Cheltenham Road, Longlevens

Resident Letter     Diversion Route

 

 

 

A46 Cheltenham Road, Painswick

Resident Letter   Diversion Route - LGV

Diversion Route - HGV

 

3/365 Brockworth Road, Churchdown

Resident Letter   

 

3/83 Stoke Road, Stoke Orchard

Resident Letter     Diversion Route

 

 

 