

UPDATE: August 29th 2024.
We have managed to tie in the existing gully pipe into our 1200mm manhole, reshape the ground around it with clean stone and the excavated soil, whilst also building a headwall upstream. Next week the company Sapphire will complete the pipe lining on Tuesday & Wednesday, with the fencing to be finished on Thursday/Friday.
We will reopen the carriageway back to two-way signals from the end of 30th August. This is to allow for some short-term monitoring over the next couple of weeks to allow monitoring of the cracking present on the southbound lane. If no further movement is noted we will resurface this lane mid-end September with the aim of removing all Traffic management whilst we continue to monitor the site longer term.
UPDATE: August 2024
As per our previous communications this planned closure was to undertake investigation of the culvert with the hope that any repairs could also be undertaken during this period. Given the silt build up in the flooded area of the field, safely locating the culvert was proving trickier than planned and required a more extensive excavation. We made the difficult decision to extend our current closure to continue working now rather than having to return later and extend the inconvenience into another period. The culvert has now been located and plans to create the new drainage elements connecting to the existing culvert under the A46, as well as regrading the land located around it, are underway. The closure is officially until the 30th August, however we are hopeful we should be complete before this date.
UPDATE: July 2024
Between 29 July - 16 August 2024, a road closure will be in place to allow us to carry out investigation and repair work.
What will be in place?
A road closure will be in place 24/7 along the A46 Painswick road, between the junction with the A4713 and Pincot Lane, as pictured below. We appreciate road closures are inconvenient, but to keep everyone safe, in this case it is necessary. We have planned the work so we can be in and out as quickly as possible. The work is planned to take place between 29 July - 16 August 2024 but because elements of the work are weather dependent the dates could be subject to change.
Diversion
A diversion route will be signposted (pictured below). Please note the diversion route is designed to include a similar class of road to the A46, to accommodate larger vehicles. We ask all drivers to follow the signed diversion route to avoid congestion on smaller local lanes.

About the work taking place
We will undertake an investigation of the culvert running underneath the carriageway. Where possible we will also use the closure to carry out any other repairs required. This is a continuation of work started previously during the winter in response to cracking that developed in the road. You can read about the issue in more detail below on this web page.
A road closure was in place on the A46 at the Pincot Lane / Wragg Castle Lane junction, approximately 2.5km south of Painswick.
On 7 March 2024 a hole was found beneath the road and temporary traffic lights were installed. Technical inspections were carried out and on 11 March and the road was closed for safety reasons as cracks have also been found at this location.