Albert Street Wall

Photo of fencing around closed path and fallen wall

Albert Street Wall is a large retaining wall in Lydney, Forest of Dean. This structure supports private land above a public footpath and road. The wall ranges from 1.5m to 5m high over an approximate 70m length.

Update 6 November 2025

The full clearance of vegetation at Albert Street Wall began on Monday 3rd November and has been paused due to operational issues. A new work date will be published here in due course. We are still expecting to begin deconstructing the wall in summer 2026. We would like to thank the local community for their continuing patience. 


Previous updates

Update 16 October 2025

Extensive clearance of vegetation is planned for 3-6 November. Most vegetation above the wall (including several trees) will need to be removed to ensure the future stability of the bank. This work was previously planned for early September, but was postponed due to resource pressures. 

Our vegetation clearance will be followed by a topography survey, which provides a very clear picture of the local physics. This information is essential to ensuring the wall can be removed safely. The overhead BT cable was successfully diverted on 13 August. 

We are currently expecting to remove the wall and regrade the land in Summer 2026. We would like to thank the local community for their continuing patience. 

This repair is being managed by the Highways Infrastructure Team. We can be contacted on highwaysinfrastructure@gloucestershire.gov.uk. 


What is happening?

A partial collapse has occurred which requires immediate intervention. Large ballast bags have been installed at the base of the wall to provide structural support and the footpath has been closed. Heras fencing has also been installed to separate the collapsed wall from the public. Gloucestershire County Council aim to repair the wall during this financial year.

Work required

  • Deconstructing the full stretch of retaining wall.
  • Partial excavation of land immediately behind the retaining wall.
  • Regrading the land into a stable and safe slope. The wall will not be replaced.
     

Next steps

Our immediate next steps are:

  • De-vegetation of the work site.
  • Conducting a topography survey to better understand the local geography.
  • Diversion of existing BT Openreach cable.

Ground investigation works were completed in December 2024, which provided a much clearer picture of the conditions beneath road level.

This particular repair will require a full closure of both the public footpath and road. Access to Newerne Street carpark will be maintained throughout.

Construction is currently expected in Spring 2026.

Further details on this closure and the diversion route will be published here when confirmed. In the meantime, please direct any questions to highwaysinfrastructure@gloucestershire.gov.uk.