Sandfield Swing Bridge, Saul

Sandfield Swing Bridge is a moveable bridge that carries vehicles over the Gloucester and Sharpness Canal near Saul, and swings open from the western bank to allow watercraft to pass through. 


July 2026: joint update from The Canal & River Trust (the Trust) and Gloucestershire County Council Highways (GCC)

The Trust and GCC continue to work together to progress repairs to Sandfield Bridge and remain committed to reopening the bridge as soon as it is practical and safe to do so. 

Current position

Since the bridge was closed, the Trust and GCC have been working with engineers, contractors and specialist suppliers to develop a suitable repair solution. An initial repair approach was identified; however, as the project developed, further assessment highlighted additional considerations relating to the condition of elements of the bridge structure and the installation of the replacement bridge surfacing. These factors have required both organisations to review and refine the proposed methodology to ensure that any repairs are safe, effective and provide a durable long-term solution.

The repair works involve a number of interdependent activities for both the Trust and GCC. As a result, progress depends on aligning structural, surfacing, environmental and operational requirements before a final programme of works can be confirmed.

Environmental considerations

Environmental constraints also need to be taken into account before repair works can begin. Nesting birds have been confirmed on the bridge and ecological advice is being sought to ensure that any works are carried out in accordance with environmental legislation and guidance. The timing of these ecological constraints will influence when repairs can be undertaken.

Programme planning

Alongside the technical and environmental considerations, the Trust and GCC are coordinating their respective elements of the repair programme to ensure works can be delivered safely and efficiently, while minimising disruption to canal navigation, bridge users and local communities. This includes consideration of working arrangements and the sequencing of associated repair activities to avoid unnecessary future closures.  While a final programme has not yet been agreed, current assessments indicate that repair works are likely to take place later in the year, subject to the resolution of the remaining technical, environmental and operational requirements. Both organisations continue to explore opportunities to progress the repairs at the earliest practical opportunity.

Working together

The Trust and GCC recognise the importance of Sandfield Bridge to local residents, businesses and visitors, and appreciate the inconvenience caused by the ongoing closure. Engineers and project teams from both organisations continue to meet regularly to review progress, resolve outstanding issues and identify opportunities to progress the repairs as quickly as possible.

Further updates will be provided as additional information becomes available.

Updates

 2nd April

As the underlying structural defects have not been repaired, we will now be required to wait for the end of bird nesting season before we can undertake repairs to the bridge decking. This is expected to be in October 2026.

 

10th April

The C&RT will be holding a site visit with their asset team to inspect the structure next week.

GCC representatives and members of the design team will also be visiting for further discussions with C&RT - updates will be shared accordingly.

 

24th April

Following the C&RT site meeting last week, we are awaiting updates on the status of structure defects. Updates will be shared once we have further information.

 

28th April

When the bridge was checked, a serious problem was found with the metal strip that sits between the bridge deck and the road surface. This strip is built into the concrete part of the bridge and has badly rusted on one side. Because of this damage, it will need major repair or to be replaced completely. 

 2nd April

As the underlying structural defects have not been repaired, we will now be required to wait for the end of bird nesting season before we can undertake repairs to the bridge decking. This is expected to be in October 2026.

 

10th April

The C&RT will be holding a site visit with their asset team to inspect the structure next week.

GCC representatives and members of the design team will also be visiting for further discussions with C&RT - updates will be shared accordingly.

 

24th April

Following the C&RT site meeting last week, we are awaiting updates on the status of structure defects. Updates will be shared once we have further information.

 

28th April

When the bridge was checked, a serious problem was found with the metal strip that sits between the bridge deck and the road surface. This strip is built into the concrete part of the bridge and has badly rusted on one side. Because of this damage, it will need major repair or to be replaced completely. 

8th May

C&RT have advised us that they are liaising with their asset team following the site visit and will aim to give an update soon.

We continue to apologise for the inconvenience and thank everyone for your continued patience.

 

26th May

We are awaiting an update on current status; information will be shared as soon as it is available.

8th May

C&RT have advised us that they are liaising with their asset team following the site visit and will aim to give an update soon.

We continue to apologise for the inconvenience and thank everyone for your continued patience.

 

26th May

We are awaiting an update on current status; information will be shared as soon as it is available.

4th June

We are awaiting an update on current status; information will be shared as soon as it is available.

16th June

Whilst awaiting further information from C&RT, we have been going through the formal process of exploring options and methods for repairs. We are now liaising with external partners regarding these options and will update accordingly.

4th June

We are awaiting an update on current status; information will be shared as soon as it is available.

16th June

Whilst awaiting further information from C&RT, we have been going through the formal process of exploring options and methods for repairs. We are now liaising with external partners regarding these options and will update accordingly.

Page updated: 16/06/2026