Check this website page, social media and local signs for the latest update.
County Resurfacing Works
Investment and improvement of Gloucestershire’s Highways network is a top priority. We work in all seasons to resurface the maximum number of roads we can each year.
- See the schedule below to find out when Highways will be working in your area.
- Where possible, pedestrian access will be maintained where a designated footway is available.
- Due to the weather and other factors, dates and times may change at short notice.
- At the bottom of this page you will find official correspondence and accompanying diversion route for each resurfacing scheme.
For updates, please check local road signs and social media: follow GlosRoads on X, follow Gloucestershire Roads on Facebook
Resurfacing FAQ's can be found by clicking here. Alternatively, If you cannot find what you’re looking for email highwaysstakeholder@gloucestershire.gov.uk
Check this website page, social media and local signs for the latest update.
Many aspects need to be taken into consideration when planning works, however our resurfacing programme is dependent on several factors. It can be affected by things like; heavy rain, changes in temperatures and other weather events, as well as plant breakdown and unforeseen technical issues that arise once work has begun.
Many aspects need to be taken into consideration when planning works, however our resurfacing programme is dependent on several factors. It can be affected by things like; heavy rain, changes in temperatures and other weather events, as well as plant breakdown and unforeseen technical issues that arise once work has begun.
As the work involves hot asphalt and large equipment, we will be unable to allow traffic through the Road Closure. If you normally drive into or out of the Road Closure during the hours when the closure is in place, we ask you to please make alternative arrangements.
In exceptional circumstances, some level of access may be considered on a case by case basis but only where it does not impact our ability to undertake the necessary works and where it is safe to do so.
Please see the FAQ leaflet for further details.
As the work involves hot asphalt and large equipment, we will be unable to allow traffic through the Road Closure. If you normally drive into or out of the Road Closure during the hours when the closure is in place, we ask you to please make alternative arrangements.
In exceptional circumstances, some level of access may be considered on a case by case basis but only where it does not impact our ability to undertake the necessary works and where it is safe to do so.
Please see the FAQ leaflet for further details.
If you usually park on the road within the road closure, you will need to find alternative parking nearby during the hours of the road closure. There is a possibility that your vehicle may be towed out of the area if it is obstructing the works.
If you usually park on the road within the road closure, you will need to find alternative parking nearby during the hours of the road closure. There is a possibility that your vehicle may be towed out of the area if it is obstructing the works.
We always consider night working as an option however there are specific environmental conditions under which we are permitted to work at night, meaning often this is not feasible. We will only work at night on key routes and where the volume of traffic per day means that any potential disruption to local residents has to be balanced against the needs of the wider public.
We always consider night working as an option however there are specific environmental conditions under which we are permitted to work at night, meaning often this is not feasible. We will only work at night on key routes and where the volume of traffic per day means that any potential disruption to local residents has to be balanced against the needs of the wider public.
We appreciate that any road closure could have an impact on business operations, however to deliver the works as quickly and efficiently as possible, we kindly ask you to work with us. To help us to complete the works with the least disruption to you, we ask you to:
- Reschedule your deliveries to outside of our working hours
- Where possible, please consider if staff can park outside of the closure and walk in during our operational hours or share a lift to work to limit the number of vehicles needing access. Access to vehicles will only be considered on a case by case basis but only where it does not impact our ability to undertake the necessary works and where it is safe to do so.
- Keep your customers up to date with details of the road closure and give them details of how and when they will be able to get to you.
We appreciate that any road closure could have an impact on business operations, however to deliver the works as quickly and efficiently as possible, we kindly ask you to work with us. To help us to complete the works with the least disruption to you, we ask you to:
- Reschedule your deliveries to outside of our working hours
- Where possible, please consider if staff can park outside of the closure and walk in during our operational hours or share a lift to work to limit the number of vehicles needing access. Access to vehicles will only be considered on a case by case basis but only where it does not impact our ability to undertake the necessary works and where it is safe to do so.
- Keep your customers up to date with details of the road closure and give them details of how and when they will be able to get to you.
In most circumstances we will distribute letters before we start work to notify those within the road closure of the up coming works. The best place to get the most up-to-date information is via road signs, this web page and our social media channels. At the bottom of this page you will find letters with detail about each resurfacing scheme and the official diversion route.
In most circumstances we will distribute letters before we start work to notify those within the road closure of the up coming works. The best place to get the most up-to-date information is via road signs, this web page and our social media channels. At the bottom of this page you will find letters with detail about each resurfacing scheme and the official diversion route.
Structural Maintenance Resurfacing Programme
June 2026 - July 2026
Resurfacing works are delivered Monday to Friday, scheme dates below do not include weekends unless otherwise stated.
(Updated on 5th June 2026)
|
District |
Scheme |
Operational |
Planned Start Date |
Planned End |
| Forest |
4/481 Glebe Road & Vauxhall |
Restricted Days (09:00 to 15:00) |
01/06/2026 |
10/06/2026 |
| Cotswold |
3/130 Moreton Road |
Restricted Days (09:00 to 15:00) |
02/06/2026 |
10/06/2026 |
| Tewkesbury |
A46 & 3/380 Crosshands Roundabout |
Nights (20:00 to 07:00) |
03/06/2026 |
11/06/2026 |
| Forest |
B4221 Ross Road |
Nights (19:00 to 07:00) |
10/06/2026 |
12/06/2026 |
| Cotswolds |
3/130 Moreton Road |
Unrestricted Days (07:00 to 19:00) |
11/06/2026 |
19/06/2026 |
| Tewkesbury |
4/3115 Orchard Road |
Restricted Days (09:30 to 15:30) |
12/06/2026 |
15/06/2026 |
| Tewkesbury |
4/2422 Grove Road |
Restricted Days (09:30 to 15:30) |
16/06/2026 |
17/06/2026 |
| Tewkesbury |
4/2493 Yarnolds |
Restricted Days (09:30 to 15:30) |
18/06/2026 |
19/06/2026 |
| Forest |
3/63 from A417 Ledbury Road to M50 Bridge |
Restricted Days (09:30 to 15:30) |
18/06/2026 |
24/06/2026 |
| Gloucester |
3/215 Sneedhams Green |
Unrestricted Days (07:00 to 19:00) |
19/06/2026 |
19/06/2026 |
| Tewkesbury |
4/5781 Lawn Crescent |
Restricted Days (09:30 to 15:30) |
22/06/2026 |
23/06/2026 |
| Cotswold |
A44 London Road |
Nights (20:00 to 07:00) |
22/06/2026 |
30/06/2026 |
| Tewkesbury |
4/7961 Parton Road |
Restricted Days (09:30 to 15:30) |
24/06/2026 |
25/06/2026 |
| Tewkesbury |
B4080 Bredon Road |
Nights (19:00 to 07:00) |
25/06/2026 |
30/06/2026 |
| Forest |
B4208 Malvern Road |
Nights (19:00 to 07:00) |
25/06/2026 |
02/07/2026 |
| Cotswold |
3/332 Hangmans Stone to Countryside Museum |
Unrestricted Days (07:00 to 19:00) |
26/06/2026 |
02/07/2026 |
| Tewkesbury |
3/80 Innsworth Lane |
Restricted Days (09:30 to 15:30) |
26/06/2026 |
07/07/2026 |
Details of resurfacing works in your area

4/481 Glebe Road & Vauxhall Newent
B4221 Ross Road Kilcot
3/63 from A417 Ledbury Road to M50 Bridge Redmarley
B4208 Malvern Road Staunton
4/481 Glebe Road & Vauxhall Newent
B4221 Ross Road Kilcot
3/63 from A417 Ledbury Road to M50 Bridge Redmarley
B4208 Malvern Road Staunton
3/130 Moreton Road Longborough (section 2)
3/130 Moreton Road Longborough
A44 London Road Moreton-in-Marsh
3/332 Hangmans Stone to Countryside Museum Hampnett
3/130 Moreton Road Longborough (section 2)
3/130 Moreton Road Longborough
A44 London Road Moreton-in-Marsh
3/332 Hangmans Stone to Countryside Museum Hampnett
No Works Currently Planned for Cheltenham
No Works Currently Planned for Cheltenham
No Works Currently Planned for Stroud
No Works Currently Planned for Stroud
A46 & 3/380 Crosshands Roundabout Brockworth
4/3115 Orchard Road Bishop's Cleeve
4/2422 Grove Road Churchdown
4/2493 Yarnolds Shurdington
4/5781 Lawn Crescent Shurdington
4/7961 Parton Road Churchdown
B4080 Bredon Road Mitton Tewkesbury
3/80 Innsworth Lane Innsworth
A46 & 3/380 Crosshands Roundabout Brockworth
4/3115 Orchard Road Bishop's Cleeve
4/2422 Grove Road Churchdown
4/2493 Yarnolds Shurdington
4/5781 Lawn Crescent Shurdington
4/7961 Parton Road Churchdown
B4080 Bredon Road Mitton Tewkesbury
3/80 Innsworth Lane Innsworth