What is the timeline?
•    Submit our information return by 5 April 2024. The information return is a set of core documents and data and includes our self-assessment.
•    Expect on-site inspection within six months, with six weeks’ notice provided (Update - on 8 July CQC confirmed their intention to start their onsite inspection on 2 September 2024.)
•    We provide CQC with case tracking* anonymised information 10 days after notification from CQC of onsite visit
•    This means that we can expect to be inspected between mid-May and mid-October (Update - now confirmed as 2 September 2024)
CQC assessment - six stage process
1.    Notice of assessment - 18 March 2024
2.    Information return request - 5 April 2024
3.    CQC review of publicly available data
4.    Onsite CQC assessment visit - now confirmed as 2 September 2024. On 8 July we were given 10 days to return case tracking from notification.
5.    Date TBC post inspection - CQC provide draft report and rating
6.    Date TBC post inspection - Final report and rating factual accuracy check and then publicly published
________________________________________
*Follows pathway i.e. a person’s 'journey' from the initial approach to the local authority, to assessment, care planning, moving through services (if applicable), impact, outcomes, and review.