Frequently Asked Questions (FAQs)

Why has the A435 at Colesbourne been closed?

The road has been closed because monitoring identified a significant increase in ground movement following heavy rainfall.

Approximately 20mm of movement was recorded within a 24-hour period, and cracking had extended into the running lane. For the safety of road users, we took the decision to close the road while further investigations are carried out


How long will the A435 be closed?

At this stage, we cannot give a confirmed reopening date.

We first need to understand the ground conditions, the cause and extent of the movement, and what repairs will be needed to make the road safe.

We know the closure is disruptive and we are working as quickly as possible to complete the investigations. We will update this webpage as soon as we have more information.


What investigations are being carried out?

A programme of investigation work is underway to help us understand what is happening beneath the road.

This includes:

  • Clearing the carriageway so the cracking can be fully inspected
  • Surveying and accurately mapping the affected areas
  • Ground Penetrating Radar (GPR) surveys
  • Trial holes across the carriageway and verge
  • Continued monitoring and inspection by our geotechnical specialists.

What are trial holes and why are they needed?

Trial holes are small areas excavated through the road and surrounding ground so our engineers can see and investigate the materials and conditions beneath the surface.

Five trial holes are currently planned across the affected area. The information gathered will help us better understand the ground movement and determine what further work is required.


Has there been movement here before?

Yes. This section of the A435 has a history of ground movement and has been monitored for a number of years.

Historically, cracking affected around 25 metres of the carriageway. During an inspection in August 2025, the affected area was found to have increased significantly, extending for approximately 100 metres. Further cracking was identified during 2026 and the site continued to be monitored.


Why can't you just repair the road and reopen it?

The visible cracking is a result of movement below the road surface. Simply resurfacing the carriageway would not necessarily address the underlying cause.

We need to understand the ground conditions and what is causing the movement before deciding on the most appropriate repair.

This will help us develop a solution that is safe and appropriate for the site.


Why can't temporary traffic lights be used instead?

Temporary traffic signals had been used to manage traffic around the affected section.

However, the condition of the site changed and cracking extended beyond the area covered by the temporary traffic management and into the running lane. Approximately 20mm of movement was subsequently recorded over 24 hours.

Given the level of movement, closing the road was necessary to protect road users and allow investigations to take place safely.


When will we know what repairs are needed?

The investigation work needs to be completed and the findings assessed before the most appropriate repair can be confirmed.

Once we better understand the cause and extent of the movement, we will be able to determine what work is required and provide more information about the next steps.


 

Why has the A435 at Colesbourne been closed?

The road has been closed because monitoring identified a significant increase in ground movement following heavy rainfall.

Approximately 20mm of movement was recorded within a 24-hour period, and cracking had extended into the running lane. For the safety of road users, we took the decision to close the road while further investigations are carried out


How long will the A435 be closed?

At this stage, we cannot give a confirmed reopening date.

We first need to understand the ground conditions, the cause and extent of the movement, and what repairs will be needed to make the road safe.

We know the closure is disruptive and we are working as quickly as possible to complete the investigations. We will update this webpage as soon as we have more information.


What investigations are being carried out?

A programme of investigation work is underway to help us understand what is happening beneath the road.

This includes:

  • Clearing the carriageway so the cracking can be fully inspected
  • Surveying and accurately mapping the affected areas
  • Ground Penetrating Radar (GPR) surveys
  • Trial holes across the carriageway and verge
  • Continued monitoring and inspection by our geotechnical specialists.

What are trial holes and why are they needed?

Trial holes are small areas excavated through the road and surrounding ground so our engineers can see and investigate the materials and conditions beneath the surface.

Five trial holes are currently planned across the affected area. The information gathered will help us better understand the ground movement and determine what further work is required.


Has there been movement here before?

Yes. This section of the A435 has a history of ground movement and has been monitored for a number of years.

Historically, cracking affected around 25 metres of the carriageway. During an inspection in August 2025, the affected area was found to have increased significantly, extending for approximately 100 metres. Further cracking was identified during 2026 and the site continued to be monitored.


Why can't you just repair the road and reopen it?

The visible cracking is a result of movement below the road surface. Simply resurfacing the carriageway would not necessarily address the underlying cause.

We need to understand the ground conditions and what is causing the movement before deciding on the most appropriate repair.

This will help us develop a solution that is safe and appropriate for the site.


Why can't temporary traffic lights be used instead?

Temporary traffic signals had been used to manage traffic around the affected section.

However, the condition of the site changed and cracking extended beyond the area covered by the temporary traffic management and into the running lane. Approximately 20mm of movement was subsequently recorded over 24 hours.

Given the level of movement, closing the road was necessary to protect road users and allow investigations to take place safely.


When will we know what repairs are needed?

The investigation work needs to be completed and the findings assessed before the most appropriate repair can be confirmed.

Once we better understand the cause and extent of the movement, we will be able to determine what work is required and provide more information about the next steps.


 