Work updates
History of movement and monitoring
Historically, cracking affected approximately 25 metres of the westbound carriageway, which was resurfaced around 2023. Following this, regular drive-over surveys were undertaken to monitor the condition of the road.
During an inspection in August 2025, engineers found that the affected area had increased significantly and extended for approximately 100 metres. Subsidence and cracking were identified at several locations along the carriageway, with approximately 60mm of movement recorded in one area.
Further cracking was identified during 2026, and our geotechnical team continued to monitor the site. The site has also been identified as being particularly vulnerable following periods of prolonged or heavy rainfall.
Temporary traffic signals had been in place to safely manage traffic around the affected area. However, following recent heavy rainfall, movement accelerated and the cracking extended beyond the limits of the traffic signals and into the running lane.
On 19 November, approximately 20mm of ground movement was recorded in just 24 hours. Due to this significant change, we took the decision to close the road.