Work updates
Work updates
Update: 11th November 2026
Site 1a
Work to install the piles, which help stabilise and strengthen the road, was successfully completed on 27th October.
The team is now clearing the site and preparing for the next stage of work, including installing kerbs and resurfacing the road. This brings Site 1a another step closer to completion.
Site 2
Work is also progressing well at Site 2. Preparations for the piling works have now been completed, including preparing and testing the working area and carrying out excavation works.
Permanent piling began on 9th November. This is an important stage of the work needed to stabilise this section of Forest Road.
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
![]() |
Montel Newsletter - Forest Road September 2026 Newsletter
Montel Newsletter - Forest Road September 2026 Newsletter
Montel Newsletter - Forest Road June 2026 Newsletter R2
Montel Newsletter - Forest Road June 2026 Newsletter R2
Montel Newsletter - Forest Road March Newsletter
Montel Newsletter - Forest Road March Newsletter
Montel Newsletter - Forest Road February 2026 Newsletter
Montel Newsletter - Forest Road February 2026 Newsletter









