Work updates
Current Status
Project phase: Design and development
Recent activities have included:
- Ground investigations completed
- Site monitoring ongoing
- Engineering assessments undertaken
- Detailed design development in progress
- Construction works to be confirmed (anticipated November 2027.)
- Permanent stabilisation works to commence
- This section will be updated as the project progresses.
Construction programme
The construction programme revised to reduce impact on cattle grazing
Main construction works were originally expected to begin sooner. However, following discussions with local stakeholders and commoners, concerns were raised about the potential impact that major construction activities could have on cattle grazing during the spring and summer months.
After carefully considering this feedback, the project programme has been revised. Subject to the completion of the detailed design and necessary approvals, the main construction phase is now proposed to begin in November 2027.
Latest Update - October 2026
Work continues on the development of a permanent engineering solution for the Cowcombe Hill landslip.
Specialist engineers are reviewing investigation findings and progressing detailed design work. Site monitoring remains in place and the condition of the slope continues to be assessed.
Further updates will be provided as key project milestones are reached.
